The tradesman must send his concerns to the client in writing and clearly outline the possible consequences.

The tradesperson must send their concerns to the client in writing and clearly outline the potential consequences. (Photo: © catalin205/123RF.com)

Read aloud:

Warning: How tradespeople can avoid liability traps

Any tradesperson working on a construction site who wants to protect themselves from liability for the mistakes of others must inform the client of any concerns they may have regarding the preliminary work of other trades. We explain how to formulate and submit these concerns correctly.

Many trades work closely together on construction sites – from excavation to tiling. Coordination errors are common. If there are deficiencies in the preparatory work , subsequent companies can fall into a liability trap . For example, a flooring installer is liable for moisture damage to parquet flooring if they fail to check the screed's readiness for covering and lay the flooring on a substrate that is too damp, even if their work was technically sound.

Tradespeople are therefore often responsible for work they themselves did not perform. For this reason, craft businesses and construction companies must check whether client specifications or preliminary work affect their own work. This requires specialized knowledge. According to Julia Gerhardter, a lawyer specializing in construction and architectural law at Ecovis , the duty of care is highest when dealing with client-supplied materials , but lowest when it comes to architectural planning.

The three pillars of an effective notice of concern

Construction contract law requires a notice of concern for legal protection . This notice must meet strict criteria to ensure that liability truly transfers to the client – ​​usually the building owner. "A common mistake is addressing the wrong person," explains lawyer Gerhardter. "The warning must not only be sent to the responsible architects, but must be addressed directly to the building owner , unless a power of attorney for the architect has been provided."

Furthermore, the form and clarity of the notification play a crucial role: A verbal complaint or a brief statement is insufficient . "The notification must be in writing for later verification purposes and must clearly state the potential consequences ," Gerhardter warns. The tradesperson must inform the client not only of the issue being raised but also specifically of the resulting risk.

You might also be interested in:

The time factor is also critical. The tradesperson must send the notification immediately as soon as the defect is apparent, ideally even before starting their own work.

No answer – what now?

In construction practice, the question often arises as to what happens after a notice of defects has been sent. Is the contractor allowed to simply continue working ? Arndt Wilkes, a lawyer at Ecovis, advises caution: "We strongly recommend waiting for an explicit response from the client ." If no response is received, contractors should send a second letter and set a clear deadline . This letter can state that work will resume after the deadline has passed. "To protect themselves against downtime costs, contractors should simultaneously submit a formal notice of hindrance ," advises lawyer Wilkes.

The situation is particularly sensitive when the client explicitly requests a design that contradicts recognized engineering standards. Especially with such special requests, an unambiguous statement of concerns is essential to legally document the other party's assumption of risk.

Overview : Register your concerns – More important than you think! > Read more here! The advisors at the Chambers of Skilled Crafts are happy to help you with legal questions!

DHB now also available digitally! Simply click here and register for the digital German Crafts Journal (DHB).

Text: / handwerksblatt.de

You might also be interested in: