Construction site is at a standstill: Is the tradesman allowed to stop work?

Delays on construction sites are commonplace in the trades. But is it permissible to simply abandon a project in such a case? A court ruling shows that only thorough documentation protects against financial loss.

Construction delays are part of everyday life for a tradesperson. Other clients are waiting, and employees and time are already allocated. So, should you just abandon the current job ? Better not: A court ruling clarifies the rules of the game to ensure payment and maintain good relations with the client.

The case

A roofing company accepted a contract to roof a sports hall. The contract stipulated clear deadlines for completion. However, because other tradespeople finished their preparatory work late , the roofer was unable to start on time. The deadlines expired, and the company subsequently ceased work, citing a lack of staff, delays from other trades, and the absence of scaffolding, which was necessary for safety.

The client then terminated the contract without notice. The roofer subsequently sued for his payment.

The judgment

The roofer's appeal to the Higher Regional Court (OLG) Naumburg was unsuccessful. 

You might also be interested in:

If a construction hindrance ceases – for example, after preliminary work is completed – the contractor must resume work immediately, the Higher Regional Court clarified. The fact that the roofer failed to do so here constitutes a serious breach of duty. He cannot claim that the contractual deadlines had expired.

"The fact that construction delays have rendered the contractually agreed-upon dates and deadlines invalid in no way releases the contractor from any obligation to perform within a specific timeframe," the ruling stated verbatim. The lack of scaffolding also did not entitle the roofer to refuse to work. He had therefore breached his contractual obligations.

The building owner has thus achieved his extraordinary Right of termination to §§ 8 Para. 3 No. 1 in conjunction with 5 Para. 4 VOB/B The Higher Regional Court ruled that the right of termination was exercised correctly. This right of termination can also apply to a VOB/B construction contract. Section 648 a paragraph 1 of the German Civil Code result. 

Naumburg Higher Regional Court, Judgment of July 22, 2025  Ref. 2 U 70/24

practical tip

"The ruling makes it clear that the contractor cannot wait after the obstacle has been removed ," explains Sabine Schönewald, legal advisor for civil and commercial law at the Cologne Chamber of Skilled Crafts and head of the mediation office. "At the client's request, he must begin work immediately and do everything reasonably possible to enable its continuation. "

What tradespeople need to know about construction delays

  • Delays justify not the work ethic.
  • Without compelling reasons Plot You must not stop working. Otherwise, you will lose your entitlement to remuneration and risk dismissal.
  • Follow-up orders and staff shortages only provide relief if you address them early, specifically, and comprehensibly. announce.

Checklist for tradespeople

  • Show delays immediately written Report the issue to the client. State the cause, the start date, and the person responsible.
  • Secure supporting documentsFor example, photos, construction logs, records, and correspondence. Because you need to prove the obstruction.
  • Report capacity bottlenecks as early as possible and specify a realistic estimate. Alternative date.
  • Report Additional costs immediately. 
  • Fordern Sie Compensation or claims for damages are justified and timely.
  • Set a deadline and offer solutionsSet a reasonable deadline for the client. Deadline Coerce them into cooperation with the threat of termination. Offer alternative safeguards or a new schedule. Remember: Cooperation strengthens your position in any future dispute!
  • If in doubt, have the legal situation checked before you stop work. A misjudgment could cost you the contract price.
  • It's best to arrange it now. in the contract All relevant points. These include important deadlines, obligations of upstream trades, scaffolding and safety issues, as well as cost sharing in case of delays.

Conclusion: Documentation protects against disputes

"Always react to delays with thorough documentation and early notification ," advises Schönewald. "Talk to the client. Those who follow these principles secure their own claims and avoid problems, termination of contracts, and payment defaults."

Source: Cologne Chamber of Skilled Crafts

The advisors at the Chambers of Crafts will be happy to help you with any legal questions!