Renovation sprint: Energy-efficient renovation of residential buildings in 22 days

The state capital of North Rhine-Westphalia, Düsseldorf, is planning a renovation sprint with the trades: Ronald Meyer's innovative method makes it possible to comprehensively renovate residential buildings within 22 days.

The concept of the renovation sprint originated with civil engineer Ronald Meyer and has already been implemented in Cologne, Hamburg, and Leipzig. Now, the renovation sprint is set to launch in Düsseldorf, the capital of North Rhine-Westphalia . The goal is to complete the renovation of residential buildings within 22 working days . A renovation coach supports a team of tradespeople in implementing this concept. The coach organizes a comprehensive building renovation, coordinating all relevant trades.

The first completed projects demonstrate that this ambitious timeline is achievable. All processes are seamlessly integrated , and the building is quickly ready for occupancy again. Electricians, heating engineers, roofers, carpenters, and all other trades are concentrated on one construction site and deployed in a coordinated manner.

The concept developed by Ronald Meyer (known from the RTL II series "Zuhause im Glück" and various ARD advice programs) is generating considerable interest in the construction and renovation trades: Around 60 tradespeople accepted an invitation from the state capital, the district craft association, and the Düsseldorf Chamber of Skilled Crafts to an information event. The state capital of Düsseldorf is supporting the introduction of the renovation sprint together with the Chamber of Skilled Crafts, the district craft association, the homeowners' association Haus & Grund, and the Düsseldorf Environmental Academy.

Achieving a higher renovation rate in existing buildings

➡️ The goal is to increase the rate of energy-efficient building renovations. This rate has stagnated at 0,7 percent per year for many years, even though the renovation of existing buildings plays a central role in achieving climate goals.

You might also be interested in:

Over 15 tradespeople from the Düsseldorf area spontaneously expressed their interest in implementing the process during the event. They must adhere meticulously to a construction schedule broken down to the hour on the building site. Only in this way can the energy-efficient renovation be completed within the planned timeframe. The interested companies are taking on this challenge under the guidance of a renovation coach.

The trades' response to serial renovation

The skilled trades have high hopes for this: the renovation sprint could be their answer to serial renovation. "With serial renovation, efficiency comes from industrial prefabrication. The danger is that the business bypasses regional tradespeople. With the renovation sprint, this efficiency comes from within the company itself, and thus the added value remains in the region," says Frederic Ferber, head of the Center for Environment, Energy and Climate at the Düsseldorf Chamber of Skilled Crafts . The Environmental Academy will train tradespeople in the renovation sprint as part of its continuing education program and ensure that the added value remains with local craft businesses.

Lutz Denken , head of the Düsseldorf Environmental Academy , says: "We are delighted by the commitment of our Düsseldorf craft businesses to engage with the concept of the renovation sprint and to pursue further training accordingly. Renovations using the sprint method benefit everyone involved: the craft businesses and the homeowners through precisely adhered-to construction timelines, and the climate because more buildings can be renovated in the same amount of time!"

What happens next? On November 5, 2026, an event for property owners will be held at the EUREF Campus in the state capital. There, they can express their interest in a renovation sprint. The first renovation sprint is scheduled to start in 2027.