Asbestos work: Companies will need a permit from December onwards.
From December 20, 2026, companies carrying out demolition work involving asbestos will be required to apply for a permit. This is due to the new Hazardous Substances Ordinance.
Construction and trade companies face a critical deadline: The new Hazardous Substances Ordinance requires them to apply for a new permit for certain asbestos-related work in existing buildings starting December 20, 2026. The transitional period, which allowed this work to be carried out without official authorization, expires on that date. The German Social Accident Insurance Institution for the Construction Industry (BG Bau) warns: Those who ignore this will face penalties and construction shutdowns.
What's new is that demolition work in the low (below 10.000 fibers/m³) and medium risk categories (below 100.000 fibers/m³) now also requires a permit. Until the end of 2025, companies only needed official permission for high-risk work (over 100.000 fibers/m³). Demolition work includes the complete removal of asbestos-containing building components or materials. This includes, for example, the removal of asbestos-containing floor coverings or the extensive removal of asbestos-containing plaster and tile adhesive.
The approval process
For asbestos demolition and dismantling work, the occupational safety and health authority – for example, the trade supervisory office – requires an application . The permit is applied for with the so-called company-specific notification . Important: Existing notifications must also be amended to include this permit before the deadline.
After submitting the application, the permit is considered granted after four weeks , provided the authorities do not raise an objection . You may only begin work after this period has expired if you do not receive written confirmation.
What this means for your business:
- Before starting work, check whether Asbestos It may be contained (for example, in old floor coverings, roof tiles, fillers). If Yes, You must obtain approval via a company-related matter. Advertising Apply to the authorities.
- You need to make all employeesList by name those who work with asbestos-containing materials. proof about their training courses and basic knowledge of asbestos handling. Please attach proof of this. occupational health Employee welfare is provided.
- Does the authority respond within four weeks If not, the permit is automatically considered as granted.
- The permit is valid six years – then you will have to reapply.
Companies should now check whether they meet all the requirements and submit their applications in time.
Exceptions to the approval requirement
Work carried out as part of functional maintenance does not require a permit. A company-specific notification is still sufficient . However, the German Social Accident Insurance Institution for the Construction Industry (BG Bau) advises applying for a permit as a precaution, since the distinction from demolition work is often difficult. Those who already hold a permit for work in high-risk areas do not need to apply for an additional permit.
Support from the BG Bau
The BG Bau (German Social Accident Insurance Institution for the Construction Industry) helps companies implement the new regulations – with advice, training and suitable practical guides. Templates for notifications and documentation can also be downloaded there.
The advisors at the Chambers of Crafts will be happy to help you with any legal questions!